ELECTRICAL

Project Name: 115 KV Transmission Line

Location: Piti to Harmon, Guam                                                                                                                                                Start Date: February 15, 2000                                                                                                                                             Date Completed: December 1, 2002                                                                                                                                   Client: Guam Power Authority

 

PROJECT DESCRIPTION

The project involved construction of a 115-kV circuit from the new Piti 115-kV Substation to the Harmon Substation.  The project is 13 miles long and was built along urban and semi-urban streets and roads.  The construction included a new 927.2 AAAC 11 5-kV circuit on porcelain horizontal post insulators with under builds, or provisions for under builds. The under builds include 34.5 kV, 13.8-kV, secondary and communications. The power poles for the project are identified consecutively from Piti to Harmon as # 1 to # 365 respectively. 

The Phase 1 is the north most 4.8 miles of the project and includes the installation of 111 new, self-supported, tubular steel poles on 300-foot-long maximum spans.  The existing under builds in this area were transferred to the new poles.  Upon the completion of the Phase 1, it was used to back-feed the 34.5-ky or 13.8-ky circuits to help maintain service while the construction progressed on specific sections of the Phase 2.  The Phase 1 includes the work from Pole # 201 to 217, inclusive, and Pole # 257 to 352, inclusive.

 

 

The Phase 2 is 8.2 miles long and consisted of constructing new 115-kV on the top of the 223 existing concrete poles.  The span lengths in this area generally do not exceed 200 feet.  The existing 34.5-kV and 13.8-kV circuits and other under builds were rearranged and lowered on cross arms, and the 115-kV insulators were mounted to newly fabricated steel pole-top extensions. The 34.5-kV circuit in the majority of this area will be changed to 927.2 AAAC. Included in the Phase 2 construction is the supply and the installation of 33 additional steel poles, the foundation modification of the existing 91 non-guyed octagonal concrete poles and the construction of pole foundations for the 18 octagonal concrete poles at the Agana swamp.  The installation of a guardrail system on various pole locations is also included.

 

   |  << Back  |
Home Resources Projects News & Information

Contacts

Copyright © 2008 Core Tech International Corporation. All Rights Reserved.