Project Name: Tumon Bay Infrastructure Beautification Phase 1

Location: Tumon Bay                                                                                                                                                          Date Completed: December 01, 1999

PROJECT DESCRIPTION

The main scope of work involved were road improvements, water line, sewer line, storm drainage, electrical upgrading and landscaping works. The primary objective of the project is to improve and upgrade the infrastructures and to incorporate beautification on San Vitores Road in order to provide attractive scenery to tourists including and local residents.

|   << Back  |

Within a brief time of existence since its incorporation on March 9, 1998, Core Tech International proved its unlimited capability and sincere commitment to the people of Guam by doing this multi-million complex project in a tremendously short time and in good quality that it has already become one of the ten pre-dominant contractors of the year.  Core Tech is proud to tell the story of this landmark project because of its winning team who had fought for the people through many adversities that were involved in the project.

During the initial phase of the construction, the various hotels, restaurants, and business establishments in Tumon raised their concern on the schedule of work. Even though the Construction Management Team considered the project as a two-year project originally, it was anticipated that the shortened nine-month road construction still would cause too great an impact in the operations of the various businesses in Tumon. 

 

In addition, the tourism programs of the Guam Visitors Bureau (GVB) and the Guam Hotel and Restaurant Association (GHRA) will be adversely affected by the road construction due to the inevitable heavy traffic congestion caused by the sectional road closures and various traffic rerouting. In close coordination with GVB, GHRA, the Guam Department of Public Works  (DPW), and the Office of the Governor of Guam, the “fast track” schedule on a five-month road construction was conceptualized by Core Tech.  It was agreed that the San Vitores Road would be half closed for construction and that the remaining half shall be the public access to motorists.  The southbound lanes were initially closed to allow construction of the forcemain sewer, gravity sewer, storm drainage, waterline and underground electrical.  The scope of work includes sub-base and base compaction and asphalt base restoration and replacement.  The northbound lanes were open to vehicular traffic one way north bound for three and a half months from January to mid-April, 1999. 

From April 22 to May 30, 1999, the northbound lanes of the road were closed to allow the construction of the underground primary electrical works including the sewer, water,  storm drainage and electrical laterals .  During this time, the southbound lanes were used as the public access for the motorists.  Traffic was likewise one-way in the northbound direction.               

This “fast track” construction schedule allowed the completion of the underground utilities work in just five months and the complete public access to the San Vitores Road in time for the major tourist events, namely the Japanese Festival and the “Block Party”.  The immediate road opening enabled all the businesses to resume normal operations at a much earlier time and thereby prevented possible great loss in revenue and more inconvenience brought about by the project construction.    

Every staff and management in the winning team of Core Tech, through the fast track schedule period, worked in two (2) shifts from 7:00 a.m. to 11:00 p.m. from Monday through Sunday non -stop.  It required them to be fully committed and sacrifice the important part of their lives for the general public.  It also required close coordination with the construction management team, project inspectors and the material-testing contractor to be able to successfully complete the Phase I in time.